News

  • 30.08.2019
    03.09.2019

    In August the delivery of the Scrubber Flex and Scrubber H2S coming with internal devices (a set of plates for the flow of processing media and drip collectors (demisters)) was made.
    Also the shipment of the internal devices of the end gas cooler - set of random packing of pall rings type and drip collector (demister) with support grid was made.
    The equipment was made at the request of our partner - Paul Wurth Company for coke production of JSC "ArcelorMittal Temirtau".
    Development of design documentation for manufacturing was prepared by Research Institute "CemeqMash" according to initial data of Paul Wurth Company.
    Shipment of oversized vessels was made by mounting blocks, disassembled.
    Currently, the sets of preformed packing for the shipped scrubbers are in the process of manufacturing.

  • 28.08.2019
    28.08.2019

    Balance tank with capacity of 107 cubic meters was shipped for the being built oxygen station of one of non-ferrous metallurgy enterprises.
    Equipment was manufactured according to the documentation of Research Institute CemeqMash.
    Delivery was made in time, according to contractual obligations.
    Earlier, according to this project, the following equipment was shipped:
    - Mufflers in the amount of 2 PCs.
    - Adsorbers in the amount of 4 PCs.


  • 21.08.2019
    26.08.2019

    A set of heat exchange equipment was shipped for the shop under construction of combined heat power plant at JSC “Ural Steel":

    • Coolers of condensate and continuous purging,
    • Low pressure heaters.

    Currently, 7 units of the equipment were manufactured and delivered to the Customer.

  • 21.08.2019
    26.08.2019

    A number of components and spare parts of various machines and industrial units were manufactured and shipped for partner enterprises in August 2019.

    Design documentation was developed by the specialists of research institute CEMEQMASH and agreed with the Customer.

    Deliveries were carried out in the terms established by contracts.

  • 16.08.2019
    22.08.2019

    Start-up and commissioning works and debugging of application software of МЦ 2x10,5 were completed for our partners in the Republic of Kazakhstan within the complex project for the mill replacement the mill.
    The equipment was accepted into service by the Customer.
    The whole complex of works was performed by specialists of "CEMEQ" group of companies.

  • 14.08.2019
    22.08.2019

    Erection supervision works of the drying drum Ø2х12 m were completed by the specialists of Service Department of LLC “Cemeq minerals” within the project "Reconstruction of the drying line of antimonic float concentrate".
    Technological equipment of the line was designed and developed in Working Design Documentation by the specialists of JSC Research Institute “CEMEQMASH”. The whole set of equipment was supplied by company LLC "Cemeq Minerals".
    This project confirms the demand for complex approach (design, supply, construction and assembly works and start-up and commissioning works) during the implementation of projects for the modernization of production, technical re-equipment and new construction of technological lines.

  • 09.08.2019
    14.08.2019

    Support rollers 400 tons were developed, manufactured and delivered for one of the enterprises of the processing industry of Russia.

    Design documentation was developed by designers of research institute CEMEQMASH and agreed with the Customer.

    Delivery was made in terms established by the contract.

  • 05.08.2019
    13.08.2019

    Summing up the results of the work of Automated Process Control System (APCS) department for the first half of 2019, we are confident about the successful implementation of a number of projects in the branch of automation.

    Services of the department are in demand not only within the enterprise in manufacturing and completing of equipment of Customers, but are also provided to third parties, who complete the manufactured units with means of automation and electrical machines.

    New department carried out the design of control systems....

  • 01.08.2019
    09.08.2019

    Adsorbers for under-construction oxygen station were shipped for one of the non-ferrous metallurgy enterprises.

    Equipment was manufactured according to documentation of Research Institute CemeqMash.

    Delivery was made in time according to contractual obligations.

  • 31.07.2019
    09.08.2019

    Tooth wheels of spiral classifier in the amount of 3 pieces were manufactured and shipped for one of the mining and processing plants in Russia.

    Products were manufactured according to the drawings of Research Institute CemeqMash.

    Delivery was made in time according to contractual obligations.

  • 30.07.2019
    09.08.2019

    A muffler for under-construction oxygen station was delivered for one of the enterprises of non-ferrous metallurgy.

    Equipment was manufactured according to documentation of Research Institute CemeqMash.

    In the nearest time a set of the second muffler and a batch of Adsorbers and balance tanks will be shipped.

  • 29.07.2019
    06.08.2019

    Two centrifugal-air separators were designed, manufactured and delivered for installation for one of the metallurgical enterprises of the Republic of Kazakhstan within the program on replacement of the old equipment in the grinding workshop.

    Design documentation was developed by the constructors of research institute Cemeqmash and agreed with the Customer.

    By agreement with the Customer, the delivery was made ahead of schedule stipulated by contractual obligations.

Новости 1 - 12 of 41
First | Prev. | 1 2 3 4 | Next | Last

Media about us