  • 12.09.2017
    14.09.2017

    Within the project «Expansion and reconstruction of cement production capacity of 500 thousand tons of clinker per year», the strategic partner «Mechanical-repairing complex» of PJSC «MMK» made a delivery of metal structures and technological equipment in the amount of more than 4 thousand tons to OJSC Production Association «Yakutcement».

    During the works was completed the building of:

    - chimney flue with a height of 75 meters;

    - slurry tank;

    The works on external electrical networks are on the stage of completion.

    The works are in progress ...

  • 05.09.2017
    07.09.2017

    "CEMEQ" group of companies continues to develop the supply of equipment for gold mining enterprises. Last week the delivery of the complete mill МШР-2100х2200 was made to one of the mines of our customer of NORDGOLD Group (NORDGOLD).

    The mill МШР-2100х2200 is equipped with a complete drive, auxiliary drive, stations of liquid and grease lubrication, lining, electric motor (250 kW, 720 rpm, 6000 V), the soft starter of the main engine, control system of the mill based on SIEMENS SIMATIC controller.

  • 23.08.2017
    28.08.2017

    In August specialists of CEMEQ group of companies has successfully completed the dismantling of the old mill МШР-2700х3600 of «UZTM» production and installation of a new mill МШР-2700х3600, installed by CEMEQ group of companies for JSC "Sarylakh-Antimony" (part of a Management company LLC "GeoProMining") within the packet turn-key contract for manufacture, supply, dismantling and installation of the mill МШР-2700х3600.

    The work was done efficiently and on time, as agreed with the Customer.

  • 10.08.17
    14.08.2017

    The delivery of drum cooler body 3,3х40,0 was made for the enterprise of central part of Russian Federation within the project «Increase of fire-clay production».

    The equipment is fully developed and manufactured in a short time by the specialists of JSC "Research Institute CEMEQMASH" according to the wishes of the Customer.

  • 31.07.2017
    02.08.2017

    The delivery of a set of plates for the feeder ПП-14in the number of 108 pieces was made to JSC "Ural Steel", Novotroitsk. By agreement with the customer the equipment was delivered 2 months earlier the contractual date.

    In June our company delivered a set of plates for the feeder to ПП 2-24 in number of 56 pieces.

  • 28.07.2017
    02.08.2017

    The delivery of a set of spare parts consisting of a charging tube, the upper gas-dynamic seal and a protective sleeve to it was made for the general overhaul of the shaft kiln at HBI JSC "Lebedinsky GOK.

    A differential characteristic...

  • 18.07.2017
    19.07.2017

    Completed contract

     This month the supply of technological equipment for JSC "Oskolsky EMK", which is a part of "Metalloinvest" holding, was completed; the equipment is intended for realization of a large investment project of the plant. The supplied equipment has different functions, design and is intended for the project «Technical re-equipment of metallization unit № 2 with replacement of reaction tubes of the reformer».

    In the framework of the project our company delivered the following types of equipment:

  • 17.07.2017
    19.07.2017

    The delivery of the set of process gas pipeline was completed for JSC "Oskolsky EMK", Stary Oskol. The equipment is intended for realization of the project «Technical re-equipment of metallization unit № 2 with replacement of reaction tubes of the reformer».

  • 12.07.2017
    17.07.2017

    In early July the sixth set of support stations were delivered to JSC "Apatite" ("PhosAgro" Holding) within the project of technical re-equipment of drying drums ø 3,5х27 m. The equipment was manufactured and delivered 4 days earlier the contractual obligations, which reduced the downtime of processing equipment. The first sets of stations were installed and have been working without any problems for 6 months. Design documentation was developed by specialists of JSC "Research Institute Cemeqmash".

  • 05.07.2017
    17.07.2017

    The delivery of a set of top gas scrubber was made to JSC "Oskolsky EMK", Stary Oskol, comprising: bodies, Venturi assembled, drop collector of process gas and collectors Ду150 и Ду200. The delivery of the equipment was made within the realization of the project «Technical re-equipment of metallization unit № 2 with replacement of reaction tubes of the reformer».

  • 05.07.2017
    17.07.2017

    The delivery of the mill МСЦ ø 3,2х4,5m was made for JSC "Gaisky GOK" - one of the leading enterprises of the mining complex of the Ural mining and metallurgical company (OOO "UMMC-holding"). The mill was delivered within the framework of renovation of worn-out equipment.

    Under the program of import substitution, this mill was designed and fully manufactured at the Russian plant, in compliance with the requirements for the unification of spare parts from previously used foreign equipment."

  • 28.06.2017
    10.07.2017

    Within the project «Increase of fire-clay production» the delivery of the rotary kiln body ᴓ4,0х90m was made for the enterprise the central part of Russian Federation.

    The equipment is fully developed, manufactured and delivered in a short time by the specialists of JSC "Research Institute CEMEQMASH" according to the wishes of the Customer.