News

  • 07.11.2017
    13.11.2017

    On the territory of LLC "Magnitogorsk cement-refractory plant" specialists of service department of CEMEQ group of companies performed linear-instrumental regulation of rotary kilns, namely:

    - calculating of central angles on the kiln supports;

    - definition of the rotation axis of the kiln in projection on a vertical plane;

    - definition of the rotation axis of the kiln, position of the thrust rollers and skewing of support rollers in projection on a horizontal plane;

    - alignment of position of the kiln main drive in the projection on vertical and horizontal planes;

    - recommendations on further operation.

  • 03.11.2017
    13.11.2017

    In October 2017, the service department of CEMEQ group of companies successfully began to commence service maintenance of technological equipment on the territory of LLC "Magnitogorsk cement-refractory plant" (one of the leading enterprises of the Ural region for the production of cement and dolomite, part of the Group of companies "Magnitogorsk Iron and Steel Works"(PJSC «MMK»).

  • 31.10.2017
    03.11.2017

    In September-October 2017, CEMEQ company performed installation and commissioning works at one of the sites of JSC MCC "EuroChem" according to the project: "Modernization of Drum granulator-dryer БГС ᴓ,5х35,0 and БГА ᴓ 4,0х8,0", in which engineering, manufacturing and supply of equipment "turnkey" were performed. The project was implemented jointly with a technological partner «The Research Institute for fertilizers and Insectofungicides» (JSC "NIUIF").

  • 31.10.2017
    03.11.2017

    In October the delivery of two sets of bag filter bodies of grinding and coal drying unit was made for one of the mining companies. The equipment for cleaning of flue gases was supplied by mounting blocks. Currently, the works on assembly of equipment are in progress at the installation site of the customer.

  • 03.10.2017
    06.10.2017

    In September, the specialists of CEMEQ completed general overhaul of the mill МШР ᴓ4,5x5,0 m for JSC Apatit (PhosAgro) within the contract "General overhaul of grinding complexes АНОФ-2 in 2017". The work was completed on time; our specialists started the next stage of the contract - repairing of МШР ᴓ 3,6x4,0 m.

  • 28.09.2017
    02.10.2017

    The dismantling of 30-chambers burning kiln №3 was successfully completed at JSC "ENERGOPROM-Novocherkassk electrode plant" - the largest Russian enterprise for production of graphite electrodes, the works were completed ahead of schedule.

    Currently, the brickwork of fireclay brick is in the process.

    All works are being performed by CEMEQ service department.

  • 20.09.2017
    22.09.2017

    Within the program of modernization of the main production (Drum granulator-dryer ø 4,5х35 m, ø 3,5x18 m) at the enterprise of JSC "PhosAgro" holding company the supply of equipment was performed; it was designed by the specialists of JSC "Research Institute CEMEQMASH" and performed at the production site of CEMEQ group. The equipment is delivered on time according to contractual obligations.

  • 12.09.2017
    14.09.2017

    Within the project «Expansion and reconstruction of cement production capacity of 500 thousand tons of clinker per year», the strategic partner «Mechanical-repairing complex» of PJSC «MMK» made a delivery of metal structures and technological equipment in the amount of more than 4 thousand tons to OJSC Production Association «Yakutcement».

    During the works was completed the building of:

    - chimney flue with a height of 75 meters;

    - slurry tank;

    The works on external electrical networks are on the stage of completion.

    The works are in progress ...

  • 05.09.2017
    07.09.2017

    "CEMEQ" group of companies continues to develop the supply of equipment for gold mining enterprises. Last week the delivery of the complete mill МШР-2100х2200 was made to one of the mines of our customer of NORDGOLD Group (NORDGOLD).

    The mill МШР-2100х2200 is equipped with a complete drive, auxiliary drive, stations of liquid and grease lubrication, lining, electric motor (250 kW, 720 rpm, 6000 V), the soft starter of the main engine, control system of the mill based on SIEMENS SIMATIC controller.

  • 23.08.2017
    28.08.2017

    In August specialists of CEMEQ group of companies has successfully completed the dismantling of the old mill МШР-2700х3600 of «UZTM» production and installation of a new mill МШР-2700х3600, installed by CEMEQ group of companies for JSC "Sarylakh-Antimony" (part of a Management company LLC "GeoProMining") within the packet turn-key contract for manufacture, supply, dismantling and installation of the mill МШР-2700х3600.

    The work was done efficiently and on time, as agreed with the Customer.

  • 10.08.17
    14.08.2017

    The delivery of drum cooler body 3,3х40,0 was made for the enterprise of central part of Russian Federation within the project «Increase of fire-clay production».

    The equipment is fully developed and manufactured in a short time by the specialists of JSC "Research Institute CEMEQMASH" according to the wishes of the Customer.

  • 31.07.2017
    02.08.2017

    The delivery of a set of plates for the feeder ПП-14in the number of 108 pieces was made to JSC "Ural Steel", Novotroitsk. By agreement with the customer the equipment was delivered 2 months earlier the contractual date.

    In June our company delivered a set of plates for the feeder to ПП 2-24 in number of 56 pieces.

Новости 1 - 12 of 54
First | Prev. | 1 2 3 4 5 | Next | Last

Media about us