News

  • Production and shipment of 117-stationary crusher frame
    25.09.2020

    For one of our key customers, 117-stationary crusher frame has been manufactured.

    This equipment is unique due to its weight and size and is manufactured by electric slag welding of cast walls. The weight of this frame is 90 tons.

  • Production and shipment of main shaft and 111-stationary crusher jaw
    25.09.2020

    Production and shipment of main shaft and 111-stationary crusher jaw

  • A set of maintenance works on the territory of PJSC MMK (Magnitogorsk Iron &Steel Works)
    17.09.2020

    Over the past period, specialists of Cemeq Minerals LLC Service Department completed a set of repair works on the territory of PJSC MMK:
    - Repair of the mechanical and power equipment of heating furnace №4 of mill 2000 of slitting lines plant-10
    -  repair of run-out table of heating furnaces №1, №2, №3, №4 of 2350 mill of plate production
    Works have been accepted by the Customer, closing documents have been signed.

  • Production of complete control systems for two ball mills 2,1х3.
    09.09.2020

    The Department of Automated Process Control Systems and Electric Drives has completed manufacture of complete control systems for two ball mills 2,1х3.
    Design documentation, as well as application software were carried out by the department of Automated Process Control Systems and Electric Drives.
    The control systems were manufactured at our own production site.
    Сomplete control systems have successfully passed acceptance tests before shipment.

  • Start-up and commissioning of the discharge equipment unit.
    03.09.2020

    As part of the heat and power plant construction project in Sovetskaya Gavan, specialists of Cemeq Minerals LLC commissioned discharge equipment unit, consisting of:
    Stationary side car dumper 100;
    Car pusher T-20;
    Two crushing and milling machines 2,
    Two swinging feeders1,2-12x32;
    Discharge equipment automatic process control system (SCADA)
    Installation supervision and commissioning of the discharge equipment unit was provided, application software was designed and tested.
    Equipment capacity is up to 20 gondola cars per hour.
    Discharge equipment unit is equipped with a modern automatic control system, which allows to use manual and automatic modes.
    All the work was fulfilled by the specialists with vast experience in the reloading and homogenizing equipment design, manufacture supervision and equipment commissioning.

  • Production and supply of hammer crushers 170
    03.09.2020

    As a part of the heat and power plant reconstruction project in the Republic of Kazakhstan, hammer crushers 170 were manufactured and shipped according to the requirements of the Customer's technical specification.
    Construction documentation for hammer crushers 170 was carried out by the specialists of Cemeq Minerals LLC Engineering Department and agreed with the Customer.

  • Production and supply of 2,1Х3,0М complete wet grinding mills
    03.09.2020

    As а part of the grinding section main processing equipment replacement work, two sets of 2.1X3.0M wet grinding mills with left and right drives were manufactured and shipped to one of the Volga Federal District partner enterprises.
    Manufacturing and shipment were made within the terms, established by contract.

  • Grinding of 2.14x12m drying drum tyre
    31.08.2020

    For one of the enterprises producing dry mortars, Cemeq Minerals LLC Service Department carried out grinding of 2.14x12m drying drum tyre.
    At the request of the Customer, the work has been completed within a short time without equipment shutdown.

  • The first stage of fertilizer plant construction project
    31.08.2020

    As a part of the fertilizer plant construction project for one of the leading enterprises of the chemical industry in Kazakhstan, specialists of the Research Institute CEMEQMASH completed the first stage – worked out design documentation for ф4,5х16m drum granulator-dryer. At the moment, Cemeq Minerals LLC has started the second stage - manufacture of units in the amount of 2 pcs. Documentation has been given to the production department, preparation is almost complete. According to the project service department provides installation, start-up and commissioning works.

  • Manufacturing and dispatch of lubricating stations with a capacity of 70 l / min
    27.08.2020

    For one of the largest nickel producers, 3 lubricating stations with a capacity of 70 l / min were manufactured and dispatched. These stations are used in circular lubricating systems of 3.6x5m mills.
    CEMEQ Company offers its customers a range of circular oil lubricating stations of various capacities (from 12 to 220 l / min.), depending on the main equipment.
    During production process, CEMEQ specialists carried out comprehensive stage-by-stage engineering supervision and hydraulic tests before dispatch.

  • 140/2150-boreal climate-4 type air coolers and steam trap 2000
    27.08.2020

    The following products were delivered to PJSC NLMK:
    -140/2150-boreal climate-4 type air coolers – 2 pcs.
    - steam trap 2000 designed for continuous drain of coke oven gas condensate from gas pipelines – 2pcs;
    This optional set was delivered within a short  period of time. Similar equipment has already been supplied before.

  • A set of maintenance works on the territory of PJSC MMK (Magnitogorsk Iron &Steel Works) for the first half of the year 2020.
    19.08.2020

    For the first half of 2020, specialists of Cemeq Minerals LLC Service Department completed a set of repair works on the territory of PJSC MMK:
    1. 2350 hot-rolled mill PJSC MMK plate production:
    2. 2500 hot-rolled mill PJSC MMK slitting lines plant-4:
    3. 5000 hot-rolled mill PJSC MMK:
    4. 2000 hot-rolled mill PJSC MMK slitting lines plant-10:
    5. Blast-furnace plant of PJSC MMK:
    6. Crushing and preparation plant-5 of ore dressing plant for PJSC MMK mining and processing production
    During the work progress, PJSC MMK operating and technical staff gave positive feedback on timely execution of high-quality repair of the processing equipment at the PJSC MMK divisions.

Новости 1 - 12 de 68
Début | Préc. | 1 2 3 4 5 | En avant | Dernier

Media about us