The delivery of balance tanks in the amount of 4 units was the last to complete the supply of equipment for the project of oxygen station construction. In total, 16 units of large-size vehicles were delivered under this project. Currently, the installation of mufflers and preparation for the installation of adsorbers are in progress.

The equipment was manufactured according to the documentation developed by the research institute "CEMEQMASH" on the basis of the Customer's specifications.